Groundworx, LLC v. City of Hattiesburg

by
Groundworx,LLC, appealed a judgment dismissing its breach-of-contract action against the City of Hattiesburg. After reviewing the contract between Groundworx and the City, which Groundworx attached to its complaint, the Mississippi Supreme Court was left with “no doubt” that Groundworx’s complaint was properly dismissed for failure to state a claim. Even taking all of Groundworx’s allegations as true, Groundworx could cite no contractual provision the City allegedly breached. Even if Groundworx expended millions of dollars preparing to perform under the contract, it did so before securing the necessary financing to complete the project. And unfortunately for Groundworx, the contract was clear: if Groundworx did not secure financing by a certain date, the City had the right to terminate the contract. So the Court concluded Groundworx could prove no set of facts to show the City breached the contract. View "Groundworx, LLC v. City of Hattiesburg" on Justia Law